Last summer the Housing Action Coalition (HAC) and Mission Bay Neighborhood Association (MBNA) asked the San Francisco Planning Department to consider siting housing at 900 Seventh Street rather than Amazon’s proposed 710,000 square-foot fulfillment center.
“MBNA has asked the City to study how many homes 900 Seventh Street could hold, from 1,500 up to as many as the site can reasonably support,” said Bettina Cohen, MBNA president. “We’re not out to block Amazon. We want the City to know what’s possible on six acres near Caltrain before the land is committed for decades.”
“HAC is not affiliated with any specific project or proposal. We have engaged our membership for any interest in developing the site for housing,” said Witt Turner, HAC advocacy and operations associate.
Amazon wants to tear down structures left behind by Recology, which previously owned the property, and erect a production, distribution and repair building to support parcel delivery services, along with 17,700 square-feet of office space, 3,562 square-feet of ground-level commercial space, and 13,700 square-feet of public open space at Seventh and Berry Streets. Amazon plans to begin construction in 2028 and complete it before 2030.
SF Planning is preparing a draft Environmental Impact Report (EIR) for the Amazon project. The analysis, required under the California Environmental Quality Act, will assess the scheme’s potential effect on air quality, noise and traffic, and identify ways to reduce these nuisances.
“We’re concerned about the low pay and poor working conditions Amazon may offer to workers at this fulfillment center. We’re also unhappy with the center’s potential negative impacts on traffic and business activities in Mission Bay,” said Mark Gleason, spokesperson for Teamsters Joint Council 7, which has more than 100,000 members.
“The proposal that Recology presented in 2019 for this site, with many homes in a mixed-use development, was spot-on. We’re asking Planning to keep the housing option open,” said Cohen. “The area…has seen a relatively high number of crashes…two pedestrian fatalities that have involved children…in 2023, and earlier in 2026. (Amazon wants to construct) a massive building right where Showplace Square and Mission Bay could be connecting…the Recology project was being designed to knit neighborhoods.”
In 2023, Amazon granted $25,000 to the Potrero Hill Neighborhood House to fund a new science, technology, engineering, art, and math lab for underserved local youth. The online retail giant pledged $2.4 million to the San Francisco–Marin Food Bank through June 2028, mostly in the form of in-kind deliveries. And Amazon has acted as a presenting sponsor for programming hosted by the San Francisco Standard.
“As it is, our neighbors on the Hill seem to be dismissing their Mission Bay neighbors as having legitimate concerns,” said Cohen.
“What we see is that Amazon has proposed a last-mile distribution center, which doesn’t have anything,” said Prodan Statev, MBNA corresponding secretary. “It has no homes, retail space, coffee shops, offices or labs. Their plan so far constitutes an unproductive use of land that is not beneficial to the rest of the neighborhood. In fact, the fulfillment center is likely to increase traffic, noise, and air pollution.”
Kilroy Realty recently told the Planning Commission that it’s redesigning its 6.5-acre site at Sixth and Brannan, a few blocks away, as seven buildings that could hold more than 3,500 homes, some as tall as 600 feet, along with pocket parks and a street grid. Directly across the street from the Amazon site, the SF Railyards project, which proposes about 2,500 homes and four million square feet of commercial space on 18.6 acres at Fourth, King, Townsend and Seventh Streets, is preparing its own EIR; a public scoping meeting was held last month. A single-use delivery depot with no housing, wedged between those neighborhoods-in-the-making and the Caltrain corridor, doesn’t appear to be synergistic with other developments in the area.
Patrick Hannan, San Francisco Planning Department and Department of Building Inspection communications director, said to obtain a building permit Amazon will have to demonstrate that the new facility can handle its expected energy demand.
“Amazon’s delivery stations have never impacted residents’ utility bills, and this project will be no different. We’re working closely with PG&E and will have more to share as the project progresses. We’ll continue to keep the community updated on our progress through public meetings, as we’ve done on several occasions already,” said Natalie Banke, Amazon West Coast public relations manager.
According to Banke, the company plans to outfit the Seventh Street location to accommodate e-cargo bikes, pedal-assist electric vehicles that feature a metal cargo locker at the back, with the rider situated in a semi-enclosed space. The cycles are 39.3 inches wide and 124 inches long, small enough for a standard bike lane. Amazon presently deploys them in New York City and Culver City.
“They look almost like small cars. They really challenge the definition of the term ‘bicycle,’” said Cohen.
“We’re incorporating approximately 94,000 square feet of solar panels which will generate renewable energy on-site,” said Banke, who indicated that the facility is designed to support Amazon’s Climate Pledge commitment of net-zero carbon by 2040. “We’ll have 11,500 square feet of green roof for stormwater management and energy efficiency throughout…we’re building to CALGreen standards that exceed baseline requirements. We will also have our own emergency backup generator on site.”
The spread of diesel backup generators, known as “BUGs,” is the subject of extensive research by View publisher Steven Moss. He identified 1,208 such generators in San Francisco in 2022, with a combined capacity of 736 megawatts. Across the Bay Area, the number grew 34 percent between 2018 and 2021, to 8,722. Nearly 90 percent of BUGs in the Bay Area and Southern California run on diesel.
Gleason said the Teamsters donated $5,000 to Mission Bay Elementary School last summer.
“We already work here and we want a good, safe environment for everyone. Traffic in Mission Bay is at capacity. Now Amazon wants to add numerous logistics trucks and e-cargo bikes to the situation, which will increase traffic and make the area more unsafe,” he said.
According to Hill resident Peter Belden, political chair of the San Francisco Group of the Sierra Club, that organization opposes Amazon’s fulfillment center, “because it contributes to overconsumption and pollution and reduces street safety. The plans for the center offer one parking spot for each of the center’s 500 workers. Why not give workers free transit passes or make a contribution to subsidize the use of e-bikes with San Francisco Municipal Transportation agency?”